Before is best
1. It is best to clean the patch area with a vacuum or wash to eliminate any loose dust that will prevent good bonding for the patch.
2. Before patching wet the area where you will be applying the patch.
3. Apply your SealGreen Concrete Patch and try to make it as even as possible with the rest of the floor.
4. Let it dry to a level where the patch is hard (approximate 2 hours) before grinding the patch.
5. This will provide a nice even surface with the rest of the concrete floor.